CSAH 11 (from T.H. 27 to U.S. Hwy. 71 at Clarissa):
- Culvert replacement work has been completed.
- Pavement milling and reclamation work has been completed.
- The first lift/layer of pavement has been installed over the 7.5 miles of roadway that was reclaimed (locations where exist. pavement was ground-up with base material below).
- The contractor is currently working on paving the second and final lift/layer of pavement over the entire 17 mile project route moving from south to north. Paving work is planned for completion the week of June 26th.
- Shouldering material is planned for installation and completion the week of July 3rd.
- Roadway striping is planned for completion the week of July 10th.
CSAH 38 (from West County Line to CSAH 11):
- Pavement resurfacing work has been completed.
- Shouldering material is planned for installation the week of June 26th.
- Roadway striping is planned for completion the week of July 3rd.
CR 66 (from CSAH 21 to CSAH 7):
- The road will be open to traffic with flaggers during work to complete an overlay resurfacing of the pavement.
- Paving work is scheduled for the week of July 17th.
- Shouldering material is anticipated for installation the week of July 24th.
- Roadway striping is anticipated for completion by August 1st.