Current Work Scheduled:
(Please note that this schedule of work can and will change, but it gives a general idea of timing for work on these projects. The projects are listed in the anticipated order that work will progress. We will periodically give updates as the work is completed and schedules change.)
CSAH 11 (from T.H. 27 to U.S. Hwy. 71 at Clarissa):
- Work is scheduled to start here first and is planned for closure starting Monday, May 15th for culvert work and mid-June for paving.
- The road will be closed to thru traffic with a detour in place while culvert pipes are replaced between T.H. 27 and CSAH 10.
- The detour route will follow along T.H. 27, to U.S. Hwy. 71, to CSAH 10.
- One additional culvert will be replaced between CSAH 14 and U.S. Hwy. 71, which will be completed under traffic and will remain open during work.
- Upon completion of culvert pipe replacements, 7.5 miles of roadway will be reclaimed (exist. pavement ground-up with base material below) and re-paved.
- The areas remaining that are not reclaimed will receive a mill and overlay resurfacing of the pavement.
CSAH 38 (from West County Line to CSAH 11):
- Work is scheduled to start here the week of June 5th for paving.
- The road will be open to traffic with flaggers during work to complete a mill and overlay resurfacing of the pavement.
- Also one short 800’ long segment of roadway will be reclaimed (exist. pavement ground-up with base material below) and re-paved.
CR 66 (from CSAH 21 to CSAH 7):
- Work is scheduled to start here mid-July for paving.
- The road will be open to traffic with flaggers during work to complete an overlay resurfacing of the pavement.